When planning an industrial park power distribution solution, the voltage level you collect and distribute at matters as much as the generator capacity itself. For small and medium natural gas power plants, 400V low-voltage distribution is the common choice: simple structure, straightforward installation, lower initial investment, and multiple gas generator sets paralleling into a common low-voltage busbar.

But current is the quiet variable that grows with capacity. As installed megawatts increase, the current on the low-voltage side rises with them — and with it the busbar sizes, cable cross-sections, parallel cable runs and switchgear ratings. At some point, medium-voltage distribution stops being an option and starts being the answer. This article walks through both routes with actual numbers.

Industrial park natural gas generator power distribution system
Low-voltage or medium-voltage: the two distribution routes for a gas generator power plant.

Two Main Power Distribution Methods for Natural Gas Generator Plants

When several gas generator sets operate in parallel, their output must be collected and distributed through a properly designed electrical system. Two approaches dominate industrial practice.

Low-voltage power distribution

In a low-voltage system, generator sets typically produce 400V or 415V for 50Hz applications, or 480V for many 60Hz markets. Each generator connects through its own circuit breaker to a common low-voltage busbar. After synchronization and load sharing, the power is collected in the low-voltage paralleling switchgear and fed to the factory distribution network.

Typical configuration: Natural gas supply → gas generator sets → generator circuit breakers → low-voltage paralleling switchgear → low-voltage distribution cabinet → factory loads

Medium-voltage power distribution

For larger plants, power can be collected and distributed at medium voltage — 6.3kV, 10.5kV or 11kV, depending on the local network. Two routes exist:

  • Medium-voltage generator solution: generator sets equipped with medium-voltage alternators produce electricity directly at the required voltage.
  • Step-up transformer solution: standard 400V generator sets feed step-up transformers that raise the voltage before the medium-voltage network.

Typical configuration: gas generator sets → MV generation or step-up transformers → medium-voltage switchgear → industrial park distribution network → factory loads

The core advantage is physics: at higher voltage, the same power travels as lower current — which simplifies the main network and shrinks the low-voltage cabling dramatically.

Solution One: Low-Voltage Generator Parallel Distribution

For smaller plants, low-voltage parallel operation is practical and economical. A typical project might run two or four 250kW natural gas generator sets, each outputting 400V into a common low-voltage paralleling switchgear — the same principle behind our 1 MW two-set parallel system, scaled to the project.

Main advantages:

  • Lower initial investment. 400V gensets, LV breakers and distribution cabinets are widely available; no MV switchgear or transformer required.
  • Simple electrical configuration. Paralleling controls handle synchronization, active and reactive power sharing automatically.
  • Convenient maintenance. LV equipment is standard industrial fare for qualified electrical personnel.
  • Direct connection to factory equipment. If the plant runs 400V equipment, power distributes without voltage conversion.

Low-voltage distribution fits when total capacity is modest, busbar current stays within practical design range, the generator room is close to the main distribution point, and the factory predominantly uses LV equipment. The caveat: suitability must always be checked against actual current, short-circuit level, cable installation conditions and switchgear ratings — not assumed.

Why Low-Voltage Distribution Gets Harder as Plants Grow

The obstacle is the current itself. For a three-phase system:

P = √3 × U × I × cosφ

At constant power and power factor, lower voltage means proportionally higher current. The numbers make it concrete:

Parameter400V Distribution10.5kV Distribution
Active power1,000 kW1,000 kW
Power factor0.80.8
Three-phase current≈ 1,804 A≈ 68.7 A

For the same 1 MW at the same power factor, 400V distribution carries 26 times the current of 10.5kV. Scale to a 2 MW plant at 400V and the current reaches roughly 3,608 A. That creates three practical problems:

1. Larger cables and busbars. High current demands bigger conductor cross-sections or many parallel cables per phase: thicker copper or aluminum, larger cable trays, more complicated terminations, higher procurement and installation cost. Cable sizing must also respect installation method, ambient temperature, grouping factors, voltage drop and short-circuit withstand.

2. Higher switchgear cost. A large plant may need LV switchgear rated at several thousand amperes — specially engineered, physically larger, more expensive, harder to install.

3. More complicated installation. Ranks of thick parallel cables consume space and complicate cable management, especially where generator rooms, cable trenches and distribution rooms are tight.

Past a certain capacity, the question stops being "how do we handle the current?" and becomes "why are we generating this much power at a voltage that makes current the enemy?"

Solution Two: Medium-Voltage Power Distribution

For large gas generator projects, medium-voltage distribution attacks the problem at its root: raise the voltage, cut the current.

Option A: generator sets with medium-voltage alternators

Select natural gas generator sets with medium-voltage alternators producing 6.3kV, 10.5kV or 11kV directly — matched to the customer's network. Multiple sets connect through dedicated MV generator circuit breakers to a common medium-voltage busbar.

What you gain: distribution current drops by an order of magnitude; main cables shrink from parallel conductor banks to single runs; the plant scales cleanly into the megawatts; and compatible MV motors can be fed directly.

What it demands: MV generator breakers, MV switchgear, protection relays, synchronization and load-sharing controls, and proper grounding. For parallel operation, all units must match in voltage, frequency, phase sequence and synchronization control, with protection designed around the project's short-circuit levels.

Option B: 400V generator sets with step-up transformers

Keep standard 400V gensets and step up to, for example, 10.5kV through transformers.

Typical configuration: gas generator sets (400V) → low-voltage paralleling switchgear → step-up transformer → MV switchgear → industrial park distribution network

What you gain: full freedom in genset selection and sourcing; a path to reuse existing 400V units; reduced current on the MV side; and staged expansion — generator groups, each with its own transformer (for example, two groups of four 500 kW units, each feeding one step-up transformer, both outputs joining the common MV network).

The catch every design must respect: a step-up transformer raises voltage but does not eliminate the high current on the 400V generator side. The LV busbar, generator cables, breakers and transformer input connections still carry the full generator current and must be engineered for it. Install transformers close to their generator groups to keep high-current LV cable runs short, and calculate transformer capacity, ratio, impedance, vector group, protection coordination and short-circuit behavior against the actual system.

How to Choose Between Low-Voltage and Medium-Voltage Distribution

Selection factorLow-Voltage DistributionMedium-Voltage Distribution
Generator output400V / 415V / 480V6.3kV / 10.5kV / 11kV
Main currentHigherLower
Main cablesLarge cross-section or parallel runsLower current-rated conductors
Main switchgearLV paralleling and distribution cabinetsMV switchgear
TransformerUsually not requiredRequired for voltage conversion
Initial investmentGenerally lower for small projectsHigher equipment requirements
InstallationRelatively simpleSpecialized MV installation
Typical applicationSmall and medium projectsLarge industrial power systems

Six questions settle the decision:

  1. Total generator capacity — is the project 500 kW, 1 MW, 2 MW or 5 MW?
  2. Required distribution voltage — does the factory need 400V, or does its existing network run at 10.5kV or 11kV?
  3. Cable distance — longer distances between generator station and distribution area favor medium voltage.
  4. Load characteristics — motors, compressors, pumps, heating, or a mixed industrial profile?
  5. Existing infrastructure — MV switchgear, transformers and MV motors already on site?
  6. Expansion plans — more production capacity or more gensets coming?

Medium-Voltage Main Distribution with Low-Voltage Factory Loads

Choosing MV distribution does not force every piece of factory equipment to medium voltage. Most large facilities combine the two:

10.5kV main network → 10.5kV/400V step-down transformer → 400V distribution cabinet → factory equipment

Power crosses the industrial park at 10.5kV; step-down transformers near each production area deliver 400V to standard equipment. Large compatible MV motors connect directly through dedicated protection and control. The park gets MV transmission economics while the factories keep their existing 400V machines.

EN ENERGY: Natural Gas Generator Solutions for Industrial Power Projects

EN ENERGY supplies natural gas generator sets from 5 kW to 3 MW across the EN, Perkins, Deutz, Steyr and MWM engine platforms, and supports industrial projects with:

  • Generator set selection and configuration, from a single 500 kW Deutz genset to multi-unit plants such as our 2 MW four-set Deutz power plant.
  • Single-unit and parallel generator systems with synchronization and load-sharing controls.
  • 400V low-voltage solutions and medium-voltage configurations, subject to engine and alternator compatibility.
  • Technical evaluation of step-up transformer arrangements.

Our references span manufacturing plants, industrial parks, steel factories, mines, oil and gas fields and CNG/LNG facilities. For plants that must run 365 days a year, multiple sets can be configured to parallel according to the load profile, maintenance schedule and redundancy requirement — the approach we detailed in our guide to parallel gas generator sets for factories.

Contact EN ENERGY for Your Distribution Solution

Planning a gas power plant for an industrial park or manufacturing facility? The right electrical configuration, chosen early, avoids unnecessary equipment cost and installation pain. To evaluate your project, share:

  • Total required generator capacity.
  • Required output voltage and frequency.
  • Number and rated power of generator sets.
  • Main factory load voltage.
  • Distance between generator station and factory.
  • Existing transformers and distribution equipment.
  • Continuous operation and expansion requirements.

EN ENERGY will evaluate the configuration and recommend a practical power collection and distribution solution. Visit www.en-generator.com — reliable gas power generation for industrial applications.