This project uses 14 units open-frame 250kW gas-fired generator sets to provide power for a 100,000 cubic meter LNG liquefaction plant.
Project situation:
The power station design, equipment production, delivery and installation, and commissioning liquid production cycle totaled 35 days;
The operating load is 2000-2250kW, with 12 main units and 2 standby units in rotation.
The power station has provided uninterrupted power supply to the project since it was put into operation, and the number of power outages: 0 times;